How many homes does Township of Washington add in a year? From 2010 through 2022, New Jersey's construction data recorded 49 new housing units with certificates of occupancy in the township. Over the same 13 years it issued 24 demolition permits, for a net gain of 25 homes. That works out to roughly two net homes a year. The township had 3,425 dwelling units in 2022.
Those figures come from the township's draft 2026 Comprehensive Master Plan. The Planning Board will hear public comment on the plan Monday, November 16, and may adopt it that night. It would replace a comprehensive plan dating to the 1970s. For a buyer, the part that matters is how it treats the few homes the township actually builds, which are single-family houses going up in a town where demolitions keep pace with a large share of them.
Two Net Homes a Year, With Demolitions Close Behind
The draft plan describes Township of Washington as fully developed. It counts 1,921 acres, of which 39.97 acres, or 2.08%, are vacant, spread across 54 parcels. Most of that vacant acreage is environmentally constrained. Single-family use covers 1,057.99 acres, or 55.09% of the township, across 2,945 parcels. Multifamily use covers 77.25 acres on five parcels.
Grouped into rough five-year windows, the certificate and demolition table from the draft looks like this:
| Period | New 1- and 2-family units certified | Multifamily units certified | Demolitions | Net change |
|---|---|---|---|---|
| 2010 to 2014 | 14 | 0 | 10 | +4 |
| 2015 to 2019 | 20 | 0 | 10 | +10 |
| 2020 to 2022 | 15 | 0 | 4 | +11 |
| Total | 49 | 0 | 24 | +25 |
Between 2010 and 2014, demolitions offset ten of the 14 new units. Over the full 13 years, there were 24 demolitions for every 49 new units, so new construction here happens alongside a steady pace of older houses coming down.
The existing stock comes from one era. According to the draft, more than 64% of the township's housing stock was built between 1950 and 1969, and only 17.4% has gone up since 1980. When you shop here, you are mostly choosing among mid-century single-family houses.
Permits Picked Up in 2025, and the Plan Names the Trend
Bergen County's residential building permit table shows 24 single-unit permits authorized in Township of Washington in 2025. That is up from 17 in 2024 and the highest annual total in the 2018 to 2025 span. Every year in that span shows zero multifamily permits. Authorized permits and completed certificates measure different stages of construction, so the two series don't add together. Both point the same way, with single-family construction rising inside a fixed footprint.
The draft master plan describes that activity in plain terms:
"As a general proposition, while it is recognized that there often are efforts to enlarge single-family house sizes, and, noting a trend to tear down existing dwellings and rebuild them on a much larger scale, the Township seeks to preserve the existing character of the community's neighborhoods."
Its proposed tool is a Floor Area Ratio, a cap on house size relative to lot size, set separately for each single-family zone. The plan also calls for limits on building coverage and impervious coverage. Its stated aim is that new homes complement their neighbors "even if they are slightly larger than existing dwellings." The draft does not set any numbers. It says the FAR would be established in the township's land use ordinance.
The direction matters for both buyers and sellers. A half-acre lot under a 1950s ranch is worth partly what the house is worth and partly what could be built there. The plan itself names teardown-and-rebuild as a trend, and it signals that rebuilds may face a size limit in the future.
The Density Map Mostly Confirms What's Already Built
The draft's residential categories follow the township's existing zones:
| Plan category | Matching zone | Density | Where, per the draft |
|---|---|---|---|
| Low Density | AAA | 1 unit per acre | Northwest corner: west side of Van Emburgh Avenue toward Werimus Road south of Mill Road, Gorga Place, and Washington Avenue near Jacob Place and Horizon Court |
| Moderate Density | AA | 2 units per acre, half-acre lots | Large parts of the west, northwest/central, southeast, and a small northeastern area |
| Medium Density I | A | 2.42 units per acre | Generally the eastern portion |
| Medium Density II | BB | 4.3 units per acre | East and central areas |
| Medium Density III | n/a | 5.8 units per acre | Around and south of Schlegel Lake, many lots near 10,000 square feet |
For each tier, the draft's language is about reaffirming the current pattern. It discourages anything other than detached single-family homes on one-acre lots in the AAA area, discourages higher density in the AA area, and states that around Schlegel Lake the focus is "to reinforce this density and not permit any higher density development."
The Plan Keeps Other Housing Types Limited
The draft acknowledges the township's existing mix of detached homes, townhouses, and multifamily units, then states a policy "not to allow any more multi-family housing and townhouses beyond that which is prescribed for in this Plan" and the Housing Element. It adds that "the Township is not interested in encouraging accessory apartments and other alternative means of housing." A separate goal is "to discourage the construction of two-family dwellings."
The new housing the plan does provide for sits on two Pascack Road sites. Under New Jersey's Fourth Round of affordable housing obligations, the state assigned the township 184 affordable units. A vacant land analysis set the township's realistic development potential at 19 units, and the remaining 165 units are classified as unmet need, according to the township's Fair Share Housing summary. The draft master plan sets these limits:
- 370 Pascack Road, the Valley Bank site: a 4.9-acre parcel with a maximum of 73 dwellings, including at least 15 affordable units.
- 660 Pascack Road: a maximum of 32 dwellings, including at least seven affordable units.
As of the township's summary, no plans had been submitted for either site, and both remain proposals. The same summary covers two existing overlay sites. At Bethany, the township negotiated the allowed density up from 15 to 18 units per acre, where Fair Share Housing Center had asked for 25. At Stone Mill Gardens, the negotiated change requires only one additional unit. The township notes that neither owner has plans to sell.
The commercial side of Pascack Road also stays as it is. The draft keeps the shopping center opposite Manhattan Avenue as the township's commercial hub, held to its present height and intensity, with separate zoning for that center, for the smaller retail zone across from it, and for Seasons and Bacari Grill.
What Bergen County's Fall Numbers Add
NJ REALTORS does not publish a monthly report for Township of Washington alone, so the closest current benchmark is its Bergen County Local Market Update for September 2026. In September 2026, the county's single-family median sale price was $835,000, up 1.2% from September 2025. The year-to-date median through September was $885,000, up 4.1%. Sellers received 103.4% of list price on average, homes took 34 days to sell, and supply reached 2.6 months, up from 2.4 a year earlier. Inventory rose 7.9% to 1,118 homes.
So county inventory loosened a little this fall while homes still sold above asking. In a township where the draft counts 2.08% of land as vacant and multifamily permits have been zero every year since 2018, the added countywide supply is mostly coming from somewhere else. Locally, extra supply mostly means another existing house being listed. Buyers comparing an original-condition house with a recent rebuild can find the tradeoffs in our old versus new homes in Township of Washington guide.
Monday, November 16, at 350 Hudson Avenue
The Planning Board's special hybrid hearing starts at 7 p.m. on Monday, November 16, 2026, in the Municipal Offices Court Room at 350 Hudson Avenue, with Zoom access posted on the Planning Board page. Written comments may be submitted before the hearing under board rules, and the board may act on the plan that night. The full draft, dated November 3, 2026, is on the township's master plan page.
The council will look slightly different when any follow-up ordinance reaches it. As Pascack Press reported, the council appointed Planning Board member Michael Polito to a vacant council seat on October 19, with a term through December 31, 2027, and Daisy Velez became council vice president.
This post summarizes a draft municipal plan and is general information, not legal or financial advice. Confirm what applies to a specific property with a land use attorney, architect, or the township before you plan a purchase or a rebuild around it.
Quick Answers
What does the draft say about FAR and coverage limits? The draft describes goals and policies. It recommends FAR and coverage limits but sets no numbers, and it says a FAR would be established in the township's land use ordinance. For how any change applies to a specific lot, ask the township or a land use attorney.
Where would new multifamily homes go? The plan names 370 Pascack Road, with up to 73 units, and 660 Pascack Road, with up to 32. The township's summary says no development plans have been submitted for either site.
What does the draft say about accessory apartments? The draft states the township is not interested in encouraging accessory apartments. Current rules for a specific property belong with the township's zoning office.
If you own a mid-century house in Township of Washington, a future FAR limit could change what your lot is worth to the next buyer. The Parlay Group prices both the house and the lot, and we'll walk you through how a rebuild-minded buyer and a move-in buyer would each value your property. Let's Connect.